Lot 31 Project Update – February 22, 2013

The Lot 31 project continues to progress on schedule according to developers StonebridgeCarras/PN Hoffman. The majority of the work continues to be site excavation, sheeting/shoring and support of excavation. That will change starting next week.

The contractor will complete this session of blasting by Wednesday, February 27, (assuming no significant weather delay). Next week the first of three tower cranes will start to be erected on the site. Concrete pouring will begin in March for specific locations. Foundations, footings and a permanent drainage system will also begin installation in March.

Please note that as the concrete operation begins the project will be utilizing the Bethesda Avenue construction entrance in addition to the Woodmont Avenue entrance. The Contractor will utilize flag personnel as necessary to manage the project's truck traffic.